Project Description
William R. Gaines Jr. Veterans Memorial Park Phase II design and construction to include one (1) large pavilion, two (2) pickleball courts and sanitary utility connection to the existing park restroom.
Project Location
William R. Gaines Jr. Veterans Memorial Park
20499 Edgewater Dr.
Port Charlotte, Florida 33952
Project Impacts
The restroom building, covered parking lot, and grass parking lot adjacent will be temporarily closed beginning July 6, 2026.
Tennis courts will remain accessible using the gate at the rear of the courts.
Lead time for materials.
Latest Updates
Installation of the construction fence, silt fence, and demolition in the project area has began.
Budget
| Phase | Cost |
|---|---|
| Design | $249,900 |
| Construction | $1,847,881 |
| Total Budget | $2,097,781.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 03/12/2024 | 10/28/2025 | 12/11/2025 |
| Construction | 07/06/2026 | 10/31/2026 | |
| Turnover & Closeout | 10/31/2026 | 01/31/2027 |
Supporting Materials
Project Phase
Construction
Last Updated
07/15/2026
Project Manager
Vicki Chichura
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722106
Sponsor Department
Community Services
Design Engineer/Architect
Kimley-Horn
Construction Contractor
Jon F. Swift Construction