Project Description

The project will replace approximately 780 linear feet of 12-inch wastewater force main and approximately 1,841 linear feet of 20-inch wastewater force main that runs along Quesada Boulevard from the Master Lift Station to the Lion Heart waterway. 

Project Location

Quesada Boulevard from the Master Lift Station to the Lion Heart waterway. 

Project Impacts

Acquisition of pipe and other materials has delayed a portion of the project and has increased the overall project cost. 

Latest Updates

Installation of the 12"  and 20' force main is complete. The contractor is currently working on removing the old force main and restoration of the project area. 

Budget

Phase Cost
Construction $594,803.48
Total Budget $594,803.48
Funding source(s): Utility Renewal and Replacement Fund

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 07/14/2020 02/16/2021 02/01/2021
Construction 07/05/2021 07/29/2022 07/19/2022

Project Phase
Project Complete

Last Updated
07/19/2022

Project Manager
Hendrik Dolleman

Public Relations
Caroline Wannall
Email Public Relations

Sponsor Department
Utilities

Construction Contractor
Stevens and Layton Inc.