Project Description
Renovate Charlotte County Administration Center, Murdock Campus, Building D to accommodate the growing needs of the Facilities Construction and Maintenance Department.
Project Location
18500 Murdock Circle, Building-D, Port Charlotte, Florida 33948.Project Impacts
Weather
Florida Department of Environmental Protection
South West Florida Water Management District
Latest Updates
Meeting is scheduled for July 31, 2024, for final discussion of design development plans and move into construction documents.
Budget
Phase | Cost |
---|---|
Design | $80,000 |
Construction | $800,000 |
Total Budget | $880,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 06/08/2023 | 01/30/2024 | |
Design Development | 04/02/2024 | 10/01/2024 | |
Construction | 10/23/2024 | 10/23/2025 | |
Turnover & Closeout | 10/31/2025 | 12/01/2025 |
Project Phase
Design Development
Last Updated
07/26/2024
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
c192201
Sponsor Department
Facilities
Design Engineer/Architect
Fawley Bryant
Construction Contractor
TBD