The following information is provided to aid in completing FDEP permit applications for water and wastewater utility extensions.
Water Permit
General Permit for Construction of Water Main Extensions for Public Water Systems (PWS)
Section I: General Project Information
Item F: Name of Permittee should be the developer or owner.
Item G: PWS supplying water to project: Use Charlotte County Utilities information. The Utilities Department signs here.
Item H: PWS that will OWN the project after completion: Use Charlotte County Utilities information. The Utilities Department signs here.
Item I: Engineer of Record fills in their information here.
Section II: Preliminary Design Report for Project
Items A, B and C: Engineer of Record fills in information here.
Section III: Certifications
Item A: Permittee, owner or agent of project signs here.
Item B: PWS supplying water to project: Use Peace River data on the form if not located in the Burnt Store RO plant service area. The Utilities Department signs the form.
Item C: PWS that will OWN the project after completion: Use Charlotte County Utilities information. The Utilities Department signs here.
Item D: Engineer of Record signs and seals here.
Wastewater Permit
Application for Constructing a Domestic Wastewater Collection/Transmission System
Part I: General
Subpart A: Engineer of Record or owner/developer fills in information here.
Subpart B: Instructions.
Part II: Project Documentation
Item 1: Owner/developer/agent fills in information here.
Item 2: General project information filled in by owner/developer.
Items 3 through 5: Engineer of Record fills in their information here.
Part III: Certifications
Item 1: Permittee, owner or agent of project signs here.
Item 2: Owner of Collection/Transmission System: Unless approved as an on-site privately owned system, use Charlotte County Utilities information and the Utilities Department signs here.
Item 3: Wastewater Facility Serving Collection/Transmission System: Use Charlotte County Utilities information. The Utilities Department signs here.
Item 4: Engineer of Record signs and seals here.
Charlotte County Utilities Permit Data Sheet
3100 Loveland Blvd.
Port Charlotte, FL 33980
Phone: 941.764.4300
Fax: 941.764.4319
E. David Watson, Utilities Director
Peace River/Manasota Regional Water Plant
Permitted Capacity: 51.0 MGD
Maximum Daily Flow of past 12 Months: 47.881 MGD, Month: December 2022
PWS # 5084100
PWS # 6142734
Burnt Store Reverse Osmosis Water Treatment Plant
Permitted Capacity: 3.610 MGD
Maximum Daily Flow of past 12 Months: .1.320 MGD, Month: July 2023
PWS #6080318
General and Individual Permit Data for Most FDEP Wastewater Permits
East Port Water Reclamation Facility
Central Charlotte County
Permit #: FLA 0040291
FDEP Facility ID #: FLA 0040291
Expiration Date: November 30, 2027
Permitted Capacity: 6.0 MGD
Maximum monthly average daily flow over the last 12-month period 6.473 MGD, Month: August 2023
Maximum three-month average daily flow over the last 12-month period: 5.731 MGD, Months: July, August, September 2023
West Port Water Reclamation Facility
West Central Charlotte County
Permit #: FLA 014048
FDEP Facility ID #: FLA 014048
Expiration Date: February 24, 2026
Permitted Capacity: 1.2 MGD
Maximum monthly average daily flow over the last 12-month period: 1.354 MGD, Month: August 2023
Maximum three-month average daily flow over the last 12-month period: 0.835 MGD, Months: November 2022, December 2022, January 2023
Rotonda Water Reclamation Facility
West Central Charlotte County
Permit #: FLA 014098
FDEP Facility ID #: FLA 014098
Expiration Date: May 30, 2027
Permitted Capacity: 2.0 MGD
Maximum monthly average daily flow over the last 12-month period: 1.477 MGD, Month: October 2022
Maximum three-month average daily flow over the last 12-month period: 1.491 MGD, Months: November 2022, December 2022, January 2023
Burnt Store Water Reclamation Facility
South Central Charlotte County
Permit #: FLA 014083
FDEP Facility ID #: FLA 014083
Expiration Date: December 28, 2026
Permitted Capacity: 0.5 MGD
Maximum monthly average daily flow over the last 12-month period: 0.366 MGD, Month: September 2023
Maximum three-month average daily flow over the last 12-month period: 0.345 MGD, Months: February, March, April 2023
Submitting FDEP Permit Applications to Charlotte County Utilities
All information must be filled out.
All applicable signatures must be provided.
Submit FOUR copies of all FDEP applications.