Project Description
This project consists of the installation of concrete walking paths and the demolition of the existing paths at Tippecanoe II Environmental Park.Project Location
16529 Joppa Ave Port Charlotte FL 33948Budget
Phase | Cost |
---|---|
Design | $39,980 |
Construction | $231,000 |
Total Budget | $270,980 |
Project Phase
Construction
Last Updated
09/09/2025
Project Manager
Casey Rodman
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
Johnson Engineering
Construction Contractor
Flores Construction Co