Project Description
Design and construct a sidewalk on Sunset Boulevard East.Project Location
Sunset Boulevard East from Bermont Road to South Fairway DriveLatest Updates
This project was joined with the Marathon Blvd. Pathway project for construction. The work on Sunset Blvd. E.and the Marathon Blvd project is now complete.
Budget
Phase | Cost |
---|---|
Design | $38,395.00 |
Construction | $148,350.00 |
Total Budget | $186,745.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2021 | 11/30/2021 | 01/17/2022 |
Design Development | 02/02/2022 | 12/03/2022 | 02/28/2023 |
Construction | 07/17/2023 | 01/13/2024 | 02/28/2024 |
Turnover & Closeout | 01/15/2024 | 02/29/2024 | 03/22/2024 |
Project Phase
Project Complete
Last Updated
10/17/2024
Project Manager
Raymond Slade
Public Relations
Caitlin Jackson
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
Weiler Engineering
Construction Contractor
TBD