Project Description

Implementation of the final phase of design for the existing Master Plan. This project includes the design and construction of paved, lighted parking to replace the current grass parking near the soccer fields and the installation of a large group pavilion at the soccer fields. This project is still in the design and permitting phase for the parking lot portion of the project. 

Project Location

South County Regional Park

670 Cooper St.

Punta Gorda, FL 33950

Latest Updates

The installation of the soccer group pavilion is complete. 

The desgin of the paved parking lot is at 90% completion. Final review and acceptance of all documents is expected by October 31, 2025.

Budget

Phase Cost
Design $30,000.00
Other Costs $52,252.00
Total Budget $82,252.00
Funding source(s): Capital Improvement Project

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 06/01/2024 10/31/2025

Project Phase
Design Development

Last Updated
09/12/2025

Project Manager
Lacey Solomon