Project Description
The present district office and training facility is at the end of life cycle requiring increased maintenance costs, the office is located on Airport Road.Project Location
25490 Airport Rd, Punta Gorda, FL 33950Latest Updates
A contract has been awarded to Schenkel & Shultz, Inc. for design, the CM@Risk has been awarded to Wharton-Smith Inc. for construction.
The project Guaranteed Maximum Price (GMP) was approved by the Board of County Commissioners (BCC) on September 12, 2023.
Demo work will start once the contract has been signed and approved.
Budget
Phase | Cost |
---|---|
Design | $1,000,000 |
Construction | $8,300,000 |
Total Budget | $9,300,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/11/2021 | 08/15/2022 | 03/17/2022 |
Design Development | 08/15/2022 | 04/13/2023 | 04/14/2023 |
Construction | 10/25/2023 | 10/25/2024 | |
Turnover & Closeout | 10/25/2024 | 11/15/2024 |

Project Phase
Design Development
Last Updated
09/22/2023
Project Manager
Gary Burdahl
Public Relations
Brian Gleason
Email Public Relations
Project Number
c892102
Sponsor Department
CCSO
Design Engineer/Architect
Schenkel and Shultz Inc.
Construction Contractor
Wharton-Smith Inc.