Project Description
The currrent district office and training facility located on Airport Road, is at the end of life cycle requiring increased maintenance costs.Project Location
25490 Airport Rd, Punta Gorda, FL 33950Project Impacts
Additional work was conducted with the building pad fill material due to high moisture content. All testing is completed and passed inspection.Latest Updates
Design: Schenkel & Shultz. CM@Risk: Wharton Smith. The Charlotte County Sheriff Office, new District 4 Training Center on Airport Road received its Certificate of Occupancy on April 28, 2025. Ribbon cutting was done June 3, 2025, all went as planned. Currently in the project turnover phase to Charlotte County Sheriff Office.
Budget
Phase | Cost |
---|---|
Design | $1,000,000 |
Construction | $8,300,000 |
Total Budget | $9,300,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/11/2021 | 08/15/2022 | 03/17/2022 |
Design Development | 08/15/2022 | 04/13/2023 | 04/14/2023 |
Construction | 10/04/2023 | 06/17/2025 | 04/30/2025 |
Turnover & Closeout | 06/17/2025 | 07/17/2025 |

Project Phase
Turnover & Closeout
Last Updated
07/02/2025
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
c892102
Sponsor Department
CCSO
Design Engineer/Architect
Schenkel and Shultz Inc.
Construction Contractor
Wharton-Smith Inc.
