Rampart Boulevard Sidewalk Phase 3

Project Description

The Deep Creek Street & Drainage MSBU has requested a sidewalk be designed and constructed on Rampart Boulevard.

Project Location

Rampart Boulevard from Rio De Janeiro Avenue to Navigator Road and Rampart Boulevard to 1457 San Cristobal Avenue.

Latest Updates

The 60% plans were received and are under review by staff for comments.

Budget

Phase Cost
Design $64,000.00
Construction $308,000.00
Total Budget $372,000.00
Funding source(s): The Deep Creek Street. & Drainage MSBU has requested and are funding this project.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 12/01/2022 01/16/2023
Design Development 02/01/2023 10/31/2025
Construction 11/03/2025 09/01/2026

Project Phase
Design Development

Last Updated
09/10/2025

Project Manager
Raymond Slade

Public Relations
Chad Ray
Email Public Relations

Project Number
c412204

Sponsor Department
Public Works Engineering

Design Engineer/Architect
DRMP Inc.

Construction Contractor
TBD