Project Description
The Board of County Commissioners has requested a sidewalk be designed and constructed on Rampart Boulevard as part of the 2020 Sales Tax CIPProject Location
Rampart Boulevard from Luther Road to Rio De Janeiro Avenue.Latest Updates
The 60% plans were received and are under review by staff for comments.Budget
Phase | Cost |
---|---|
Design | $174,930.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 12/01/2022 | 02/12/2023 | 02/01/2023 |
Design Development | 02/01/2023 | 10/31/2025 | |
Construction | 11/03/2025 | 09/01/2026 |
Project Phase
Design Development
Last Updated
09/10/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Inc.
Construction Contractor
TBD