Project Description
Creation of a master plan through the park design process and phase 1 development. The project tasks consist of the following:
- Site Inventory and Analysis
- Data Gathering and Analysis
- Public Input Process
- Programming
- ADA Compliance review and recommendations
- Crime Prevention Through Environmental Design (CPTED) recommendations
- Conceptual Master Planning Alternatives
- Preliminary Master Plan
- Phasing Determination
- Permitting
- Phase 1 construction oversight
Project Location
Myakka Park, 13008 Gallagher Blvd., Englewood, FL 33981
Latest Updates
Multiple public meetings have been held and a final design concept has been approved. Contract revisions are in process with the design team in moving the project forward with the Phase 1 design development and construction administration services.
Phase 1 design development and construction administration services are underway.
30% design plans have been completed and commented on. Approval to begin the tree survey and wetland flagging has been authorized.
60% design plans have been provided for review, tree survey and wetland flagging are complete and pre-DRC is set up for end of April.
Pre-DRC approved end of April
Project is in permitting with state regulatory agencies.
Permitting has been handed over to the Army Core of Engineers (ACOE).
A reviewer for ACOE has been assigned to the project. ACOE approval can take up to 18 months.
Budget
Phase | Cost |
---|---|
Design | $129,000.00 |
Construction | $800,000.00 |
Total Budget | $929,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/29/2019 |
Supporting Materials
Project Phase
Planning and Project Approval
Last Updated
09/13/2024
Project Manager
Lacey Solomon
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722103
Sponsor Department
Community Services
Design Engineer/Architect
RWA Engineering