Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Kings Hwy Harborview Rd Intersection Improvements

Project Description

The intent of this project is to harden the intersection from future storms. This includes replacing the existing span wire traffic signals with mast arm signalization and improve streetlights. Other improvements include milling and resurfacing the intersection pavement with new signing and marking and updated pedestrian crossings.

Project Location

The roadway intersection of Kings highway and Harborview road in Port Charlotte. 

Project Impacts

Improved traffic safety. 

Latest Updates

Adrew Site Work was awarded this project as the prime contractor. Notice to proceed date for construction was 8-25-25.

*** On 3-30-26 a dump truck traveling through the intersection with the truck bed up hit the newly installed mast arm crossing Harborview Rd severely damaging it. This incident will greatly increase the completion date of this project. Mast arms have a 4 - 6-month lead time on manufacturing. ***

Completed work - ASW and Sub-contractors have poured three of the four drill shaft foundations and have since installed those three mast arms and signal heads. Additional recent work includes installation of signalization directional bores, pedestrian crossing bases, underground conduit and pull boxes. 

Recent development- FPL overhead power lines were recently relocated. ASW is putting a schedule together to be able to start the work on the SE corner of the intersection now. 

Upcoming work: ASW plans to start the work on mast arm 1-2 now that relocations are complete, as well as the power supply service pole installation, and traffic control cabinet install on the NW corner. 

Budget

Phase Cost
Engineering $148,214.00
Construction $1,435,486.95
Total Budget $1,583,700.95
Funding source(s):

Lighting Department CIP Fund - Deisgn.

FDOT Grant- Construction.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 02/13/2024 12/02/2024
Construction 08/25/2025 06/07/2026

Project Phase
Construction

Last Updated
06/02/2026

Project Manager
Zach Patchell

Public Relations
Zach Patchell
Email Public Relations

Project Number
202500062

Sponsor Department
Public Work Engineering

Design Engineer/Architect
FTE

Construction Contractor
Andrew Site Wotrk

Delivering Exceptional Service

Questions? Issues?

Contact Us