Project Description
The site sustained storm damage to several recreational facilities and buildings. The Recreation Center had insulation damage to the gym floor and drywall damage along the upper north-end walls, though it continues to serve as a FEMA Disaster Recovery Center. Playground structures were impacted, including three small shade structures.
Fencing around the sports court and hockey rink was damaged, each with approximately 100 linear feet affected. Sidewalks and trails sustained about 200 linear feet of damage. Additional impacts included damage to ten trash and recycling containers.
Public Relations:
Project Managers:
- Lonne Moore
- Nicholas Reed
Project Location
3460 North Access Road, Englewood FL 34224Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event | 
|---|---|---|---|
| Buildings | Ian | ||
| Signage | Ian | ||
| Fencing | Ian, Milton | ||
| Park Amenities | 11/10/2025 | 2/10/2026 | Helene, Ian | 
| Sidewalks, Boardwalks, Piers, Dock | 10/31/2025 | 3/16/2026 | Ian | 
Budget
| Phase | Cost | 
|---|---|
| Total Budget | $673,356.00 | 



 
                           
                           
                           
                           
      
                        
      
      
      