This page is a Disaster Recovery Site of multiple projects related to Storm Damages.

Project Description

Hurricane Ian caused extensive damage throughout the site. Roof and exterior areas were affected, including minor roof leaks, soffit damage, and electrical issues at the Tenderhouse. Mechanical and electrical systems sustained impacts, with one machine damaged, electrical panel issues reported, and a traffic light requiring full replacement.

Site conditions were heavily affected—sidewalks were completely undermined and left unsafe, and all four quadrants experienced severe erosion and slope wall failures. In addition, the waterfront fender structure was missing several planks.

Public Relations:

Project Managers:

  • Anthony Altmeyer
  • Scott Francis
  • Kelly Slaughter

Project Location

1400 Beach Road, Englewood FL 34223

Latest Updates

Description of Work Estimated Start Estimated Completion Storm Event

Parking Lot/Pavement Repairs

Milton

Buildings
(Complete)

Helene, Ian

Sidewalks, Boardwalks, Piers, Dock
(Complete)

Milton

Budget

Phase Cost
Total Budget $426,601.00
Funding source(s): Road and Bridge
Disaster Recovery Site - Tom Adams Bridge Project Image

Last Updated
10/29/2025

Public Relations
Brian Gleason
Email Public Relations

Disaster Recovery Project Site

Delivering Exceptional Service

Questions? Issues?

Contact Us