Disaster Recovery Site - Port Charlotte Beach Park

This page is a Disaster Recovery Site of multiple projects related to Storm Damages.

Project Description

The site sustained widespread damage affecting waterfront structures, park amenities, and public facilities.

Impacts include erosion at multiple locations (riprap, beach pavilion undermining, beach embankment, and concrete road collapse), the bocce boardwalk, boat ramps, fishing and canoe/kayak docks, seawalls, rec center deck, multiple pavilions, restrooms, recreation center, pool house, bath house, kiosks, and specialty fencing. Additional damages involve sidewalks, lighting, signage, benches, picnic tables, pet stations, playground shade, and other park fixtures.

Known damages include gutters, vents, and air conditioning units-where demolition, stabilization, temporary roof repairs, and dry-out have been completed-as well as water damage to the recreation center, pool storage, and pool house. Storm surges undermined pavilion slabs, with partial concrete fill mitigation already performed.

Public Relations:

  • Breanna Benevenga
  • Brian Gleason
  • Chad Ray

Project Managers:

  • Pedro Agosto
  • Lonne Moore
  • Joseph Romanelli

Project Location

4500 Harbor Blvd., Port Charlotte, FL 33952

Latest Updates

Description of Work Estimated Start Estimated Completion Storm Event

Buildings
(Construction)

08/13/2025 12/30/2026 Helene, Ian, Milton
Erosion
(Construction)
10/13/2025 01/31/2026 Idalia, Milton
Fencing
(Construction)
08/13/2025 12/30/2026 Ian, Milton
Lighting
(Construction)
08/13/2025 12/30/2026 Milton
Park Amenities
(Design & Permitting)
01/24/2025 11/01/2026 Milton
Park Amenities – Helene
(Complete)
Helene
Park Amenities – Ian
(Construction)
11/10/2025 02/10/2026 Ian
Pavilions
(Design & Permitting)
01/24/2025 11/01/2026 Ian, Milton
Sidewalks, Boardwalks, Piers, Dock
(Planning)
10/10/2025 10/10/2030 Milton
Sidewalks, Boardwalks, Piers, Dock – Ian
(Design & Permitting)
07/01/2025 08/01/2029 Ian
Signage
(Complete)
Ian

Budget

Phase Cost
Total Budget $5,156,548.03
Funding source(s): Funding Source

Last Updated
10/07/2024