Project Description
Storm damage from multiple events severely impacted park and recreational facilities, with many structures buried in sand or inundated with water. The site experienced erosion and widespread damage to playgrounds, park amenities, boardwalks, sidewalks, pavilions, buildings, lighting, asphalt, curbing and fencing caused by storm surge, strong winds, flooding, and windborne debris from multiple hurricanes.
Public Relations:
Project Managers:
- Lonne Moore
- Vicki Chichura
- Nicholas Reed
Project Location
1857 Gulf Blvd., Englewood, FL 34223Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event |
|---|---|---|---|
|
Signage |
Ian | ||
|
Parking lot/pavement repairs |
Milton | ||
|
Fencing |
Ian, Milton | ||
|
Park amenities |
9/5/2025 | 10/1/2025 | Ian, Milton |
|
Playground |
9/8/225 | 10/1/2025 | Milton |
|
Pavilions |
8/11/2025 | 8/11/2030 | Ian, Milton |
|
Sidwalks, boardwalks, piers, dock |
8/11/2025 | 8/1/2030 | Ian, Milton |
|
Lighting |
Milton | ||
|
Equipment |
Milton | ||
|
Buildings |
6/2/2025 | 8/4/2027 | Milton |
|
Erosion |
9/1/2026 | 5/1/2027 | Milton |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $8,493,550.00 |
FEMA Public Assistance
Insurance
Last Updated
11/03/2025