Disaster Recovery Site - Cedar Point Environmental Park

This page is a Disaster Recovery Site of multiple projects related to Storm Damages.

Project Description

The waterfront sustained extensive pier damage resulting in total loss of approximately 140 sq ft. timber and composite fishing pier. caused by storm surge, strong winds, flooding, and windborne debris. The Conference Center sustained roof damage from a fallen tree on the front right corner, with multiple missing soffit panels, fascia, and a damaged gutter in multiple storm events.

Public Relations:

Project Managers:

  • Lonne Moore
  • Joseph Romanelli
  • Travis Purdue

Project Location

2300 Placida Road, Englewood, FL 34224

Latest Updates

Description of Work Estimated Start Estimated Completion Storm Event

Park Amenities
(Complete)

Helene

Signage
(Complete)

Helene

Fencing
(Complete)

Ian

Sidewalks, boardwalks, piers, dock
(Design and permitting)

1/11/2023 6/11/2027 Ian, Milton

Buildings
(Planning)

6/23/2025 8/12/2027 Ian, Milton

Budget

Phase Cost
Total Budget $45,353.66
Funding source(s):

FEMA Public Assitance

Insurance

Disaster Recovery Site - Cedar Point Environmental Park Project Image

Last Updated
11/03/2025