Project Description
This project incorporates the design and construction of new turn lanes and traffic signal modifications. New left and right turn lanes will be added to Cochran and Veterans Boulevard intersection along with roadway widening, drainage improvements, signal modifications, sidewalks, and pedestrian crosswalk improvements.
Project Location
Cochran Boulevard from Peachland Boulevard to Kenilworth BoulevardProject Impacts
Inclimate weather has impacted the roadwork progress.Latest Updates
EHC Construction is currently installing base rock for the roadway widening on Cochran Boulevard, constructing concrete medians on Veterans Boulevard and grading for sidewalks in various locations. Subcontractors are onsite installing underground conduit for the new street lighting and traffic signal system. The project is currently 30% completed.
Budget
Phase | Cost |
---|---|
Design | $340,277 |
Construction | $3,341,566.53 |
Total Budget | $3,681,843.53 |
Gas Tax C411620
State Funded Grant
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/11/2019 | 08/04/2019 | 08/14/2019 |
Design Development | 09/02/2020 | 06/24/2024 | 06/21/2024 |
Construction | 05/19/2025 | 11/15/2025 |
Supporting Materials

Project Phase
Construction
Last Updated
08/27/2025
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
19-279
Sponsor Department
Public Works
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
EHC Construction