Project Description
Design and construct a sidewalk on Clevland Avenue from Duncan Road (SR17) to Riverside Drive.Project Location
Clevland Ave. from Duncan Rd. (SR17) to Riverside Dr.Latest Updates
The 100% construction plans and bid documents have been received, and all review comments have been addressed. Construction of the project is currently on hold until FY27 to allow the Seminole Gulf Railroad to complete the necessary upgrades to the railroad crossing.
Budget
Phase | Cost |
---|---|
Design | $62,010.00 |
Construction | $521,778.00 |
Total Budget | $583,788.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 04/24/2024 | 07/01/2025 | 07/31/2025 |
Construction | 03/03/2027 | 09/01/2027 | |
Turnover & Closeout | 10/01/2025 | 10/31/2025 |
Project Phase
Design Development
Last Updated
09/10/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Weiler Engineering
Construction Contractor
TBD
