SR 776 Wastewater Force Main Replacement

Project Description

This project involves upsizing the existing 6-inch sewer lines to 12-inch and 16-inch lines along SR 776 from Biscayne Drive to the Charlotte Sports Park. This is an in-kind project for the Florida Department of Environmental Protection (FDEP) Consent Order. 

Project Location

Along SR 776 from Biscayne Drive to the Charlotte Sports Park.

Project Impacts

Acquisition of pipe delayed project start.

The project is currently delayed. The department is in coordination with FDOT for directional drills and MOT approvals.

Latest Updates

Construction has begun along SR 776. Driveway access to various businesses may be impacted. 

Budget

Phase Cost
Construction $977,737.95
Total Budget $977,737.95
Funding source(s): Utility Wastewater Connection Fee Fund

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Construction 06/01/2021 12/15/2023

Project Phase
Project Complete

Last Updated
12/15/2023

Project Manager
Mike Martindell

Public Relations
Caroline Wannall
Email Public Relations

Sponsor Department
Utilities

Construction Contractor
Stevens and Layton Inc.