Project Description
This project is the design and construction of a 8' sidewalk on the North side of Rampart Boulevard as part of the 2020 Sales Tax Initative.Project Location
Rampart Boulevard from Victoria Estates to Rio De Janero Blvd.Latest Updates
-
The consultant is finalizing the 90% design plans.
-
The consultant is coordinating with FDOT regarding the I-75 overpass segment.
Budget
| Phase | Cost |
|---|---|
| Design | $148,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/01/2022 | 01/16/2023 | |
| Design Development | 02/01/2023 | 06/30/2026 | |
| Construction | 08/31/2026 | 03/31/2027 |
Project Phase
Design Development
Last Updated
04/14/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Inc.
Construction Contractor
TBD