Project Description
The site experienced erosion and widespread damage to playgrounds, park amenities, boarding piers, sidewalks, floating ADA kayak/canoe launch, restroom building, lighting, and fencing caused by storm surge, strong winds, flooding, and windborne debris from multiple hurricanes. The floating ADA canoe/kayak launch and pedestrian bridge require replacement and the boarding pier requires partial replacement.
Public Relations
Project Manager
- Lonne Moore
Project Location
1000 South McCall Road, Englewood, FL 32423Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event | |
|---|---|---|---|---|
|
Equipment |
Ian | |||
|
Playground |
Ian | |||
|
Signage |
Ian | |||
|
Park amenities |
Milton | |||
|
Buildings |
6/2/2025 | 1/20/2027 | Milton | |
|
Fencing |
10/1/2025 | 2/16/2026 | Ian | |
|
Sidewalks, boardwalks, piers, dock |
11/10/2025 | 11/10/2030 | Ian, Milton | |
|
Erosion |
11/10/2025 |
|
Idalia, Milton | |
|
Lighting |
11/10/2025 |
|
Milton | |
|
Pavilions |
11/10/2025 |
|
Milton |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $1,724,500.00 |
FEMA Public Assistance
Insurance
Last Updated
11/03/2025