Project Description
Construction of reclaimed water mains along the right-of-way of Cochran Boulevard from Quesada Avenue to Peachland Boulevard.Project Location
Cochran Boulevard from Quesada Avenue to Peachland Boulevard.Project Impacts
Crews are working within the right of way along Quesada Avenue and Peachland Boulevard.
Latest Updates
This project is complete.Budget
Phase | Cost |
---|---|
Construction | $757,902.08 |
Total Budget | $757,902.08 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 11/18/2022 | 08/29/2025 | 08/26/2025 |
Project Phase
Project Complete
Last Updated
08/26/2025
Project Manager
Hendrik Dolleman
Public Relations
Stuart Gooden
Email Public Relations
Sponsor Department
Utilities
Construction Contractor
Accurate Drilling Systems