Project Description
Demolition and complete replacement/repair of the vertical seawall, safety railing, erosion and upland walkway (adjacent to playground area restroom building) at Bayshore Live Oak Park.Project Location
Bayshore Live Oak Park
23157 Bayshore Road, Port Charlotte, FL 33980.
Project Impacts
USACE permit received.
Waiting on final FDEP and SWFWMD approval. Recieved both approvals.
Bid docs received with 100% plans. Preparing for construction procurement.
Undergoing FEMA consideration QAQC to proceed with construction bid procurement.
Budget
| Phase | Cost |
|---|---|
| Design | $116,000.00 |
| Construction | $867,184.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 02/01/2025 | 11/01/2025 |
Project Phase
Planning and Project Approval
Last Updated
11/14/2025
Project Manager
Lonne Moore
Public Relations
Breanna Benevenga
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
Weiler Engineering Corp.