Project Description
The Greater Port Charlotte Street & Drainage MSBU advisory board has requested the design and construction of a new 6' sidewalk on Dorchester, Bachmann Boulevard and Yancy Street.Project Location
This project will include the design of new 6-foot sidewalks on the Southside of Bachmann Boulevard from Atwater Street to Dorchester Street, on the West side of Dorchester Street from Bachmann Boulevard to Yancy Street, and the West side of Yancy Street from Dorchester Street to Midway Boulevard.Latest Updates
The MSBU committee vote to split this project into 2 phases for construction phase 1 will be from Midway Blvd. to Peachland Blvd. phase 2 will be from Peachland Blvd. to Atwater St. FPL is onsite relocating poles to the right of way line to allow roomto install the new watermain, drainage and sidewalk. The county contractor is installing the new watermain once complete and tested it will be tied into the houses and the old main will be removed.Budget
Phase | Cost |
---|---|
Design | $155,255.00 |
Construction | $1,700,000.00 |
Total Budget | $1,855,255.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 07/07/2020 | 02/25/2022 | 03/01/2022 |
Construction | 02/03/2025 | 03/10/2026 | |
Turnover & Closeout | 04/06/2026 | 04/30/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
03/13/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Southwest Engineering & Design, Inc. (SED)
Construction Contractor
TBD