Project Description
Design & construct a sidewalk on Willmington Boulevard.Project Location
Willmington Boulevard from Pennell Street to Roberta DriveLatest Updates
The 100% construction plans were received and bid package is being assembled. The MSBU committee has requested to wait until after the FY25 paving bids are opened to look at budgets.Budget
Phase | Cost |
---|---|
Design | $72,970.00 |
Construction | $289,000.00 |
Total Budget | $361,970.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/07/2022 | 03/01/2023 | |
Construction | 07/03/2023 | 02/01/2024 |
Project Phase
Planning and Project Approval
Last Updated
12/18/2024
Project Manager
Raymond Slade
Public Relations
Caitlin Jackson
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Giffels-Webster Engineers
Construction Contractor
TBD