Project Description
Englewood East MSBU has 5 bridges needing design and construction services to implement the FDOT maintenance and repair items for each of the respective bridges.
This project is for bridge rehabilitation construction -
Gulfstream Blvd. over Memorial Waterway - Bridge #014083
Marathon Blvd. over Sioux Waterway - Bridge #014084
Gulfstream Blvd. over Sea Mist Waterway - Bridge #014091
Wilmington Blvd. over Gondolier Waterway - Bridge #014096
Ocean Spray Blvd. over March Waterway - Bridge #014097
Project Location
Gulfstream Blvd. over Memorial Waterway - Bridge #014083
Marathon Blvd. over Sioux Waterway - Bridge #014084
Gulfstream Blvd. over Sea Mist Waterway - Bridge #014091
Wilmington Blvd. over Gondolier Waterway - Bridge #014096
Ocean Spray Blvd. over March Waterway - Bridge #014097
See Location Map
Latest Updates
Project Activities for December 2024
Construction is complete on-
Wilmington Blvd. over the Gondiler WW (#014096)
Oceanspray Blvd. over March WW (#014097)
Gulfstream Blvd. over Sea Mist WW (#014091)
Gulfstream Blvd. over Memorial Waterway (#014083)
Construction started on Marathon Blvd. over Sioux Waterway - Bridge #014084 and should be completed by January 15, 2025.
Budget
Phase | Cost |
---|---|
Design | $187,020 |
Construction | $1,047,835.95 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/10/2023 | 04/10/2023 | |
Design Development | 06/07/2023 | 03/15/2024 | |
Construction | 09/03/2024 | 03/17/2025 |
Supporting Materials
Project Phase
Construction
Last Updated
12/10/2024
Project Manager
Kelly Slaughter
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Kimley-Horn Engineers
Construction Contractor
Villa Fuerte Construction