Project Description
Demolition and complete replacement/repair of the vertical seawall and upland walkway at Charlotte Harbor Event and Conference Center.Project Location
Charlotte Harbor Event and Conference Center
75 Taylor Street, Punta Gorda, FL 33950
Project Impacts
35% plans accepted.
Waiting on USACE permit approval submitted 05/24. Still in review.
Meeting with engineer for upland walkway scope limits completed on 10/29/25. Will proceed to 90% plans while awaiting USACE permit. Expected 12/25.
Budget
| Phase | Cost |
|---|---|
| Design | $182,690.00 |
| Construction | $2,500,000.00 |
| Total Budget | $2,682,690.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 11/02/2023 | 05/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
11/14/2025
Project Manager
Lonne Moore
Public Relations
Breanna Benevenga
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
Coastal Engineering Consultants, Inc.